NOTE: This list covers full closures of interstates, ramps, bridges and primary roads, and lane closures at the bridge-tunnels and the Berkley, Coleman, High Rise and James River bridges.

Scheduled closures are subject to change based on weather conditions and other factors.

For information on the many other lane closures necessary for maintenance and construction throughout Hampton Roads, visit 511 Virginia (511.vdot.virginia.gov), download the VDOT 511 smartphone app, or dial 511.

Bridges and tunnels

Hampton Roads Bridge-Tunnel, I-64:

  • Full directional closures of I-64 west from 4th View Street (exit 273) through the Hampton Roads Bridge-Tunnel continuously from 9 p.m. Oct. 2 to as late as 5 a.m. Oct. 5. For alternate traffic routes and updated information visit the project website.
  • Additional full directional closures planned for tunnel repaving, with only one direction closed at a time. The list of all scheduled dates, alternate travel routes and updated information can be found at the project website
  • Alternating, single-lane closures in both directions Oct. 5-8 from 9 p.m. to 5 a.m.   

Hampton Roads Bridge-Tunnel (HRBT) Expansion Project:

  • Full ramp closures from as early as 8 p.m. to 5 a.m.:  
    • W. Bay Avenue on-ramp to I-64 east Oct. 5-8 
    • 4th View Street on-ramp to I-64 east Oct. 5-8 
    • I-64 east off-ramp at Mallory Street (exit 268) Oct. 7-8 
  • Single-lane closures on I-64 in both directions at the HRBT Oct. 5-9* from as early as 9 p.m. to as late as 9 a.m. 
  • Single-lane closures on I-64 in both directions Oct. 5-10* from as early as 8 p.m. to as late as 9 a.m. between Willoughby Bay Bridge and Patrol Road 
  • A series of intermittent stoppages on I-64 westbound between Mason Creek and 1st View Street Oct. 5-9* from 10 p.m. to 5 a.m.  
    • (*Closures on Oct. 9, 10 will only take place if westbound HRBT is not closed for paving operations) 
  • Flagging at Mallory Street Bridge Oct. 7-8 from 9 p.m. to 5 a.m. 

Monitor-Merrimac Memorial Bridge-Tunnel, I-664: 

  • Alternating, single-lane closures in both directions Oct. 5-8 from 9 p.m. to 5 a.m. 
  • Alternating, mobile, single-lane closures northbound Oct. 6 from 9 a.m. to 2 p.m.  

James River Bridge, Route 17:

  • Single-lane closure northbound Oct. 5 from 9 a.m. to 2 p.m. 

Elizabeth River Crossings (Downtown/Midtown Tunnels):

  • Go to DriveERC.com for scheduled closures on the Downtown Tunnel (I-264), Midtown Tunnel (Route 58) and MLK Expressway (Route 164).

Interstates

I-64, Chesapeake:

  • Full ramp closures from I-64 east to I-464 north (exit 291A): 
    • Oct. 4 
      • from 12:01 a.m. to 8 a.m. 
      • from 10 p.m. to 5 a.m. 
    • Oct. 5-9 from 11 p.m. to as late as 6 a.m. 
  • Full ramp closures from I-64 east to I-464 south (exit 291B) Oct. 5-6 from 11 p.m. to 5 a.m. 
  • Full ramp closures from I-64 west to I-464 north (exit 291A) Oct. 7-8 from 9 p.m. to 5 a.m. 

I-64, Gap Widening Segment C, James City County:

  • Single-lane closures on I-64 in both directions from the New Kent County-James City County line to Route 199/Lightfoot (exit 234) Oct. 4-10 from as early as 7 p.m. to as late as 6 a.m. 
  • Brief, intermittent stoppages on Six Mount Zion Road in both directions Oct. 5-9 from 9 a.m. to 3 p.m. 

I-64, Hampton Roads Express Lanes (HREL):

  • The Hampton Roads Express Lanes project website contains additional information on the express lanes project-related closures and traffic impacts. (vdot.virginia.gov/projects/major-projects/64expresslanes/news--traffic-alerts/)

  • An interactive map displaying long-term traffic impacts across the various Hampton Roads Express Lanes construction projects can be found at the project website. (vdot.virginia.gov/projects/major-projects/64expresslanes/long-term-traffic-impacts/)

I-64, Norfolk Reversible Express Lanes:

  • Full closure in both directions: 
    • Continuously from 8 p.m. Oct. 2 until 3 a.m. Oct. 5  
    • Oct. 4-Oct. 8 from 8 p.m. to 3 a.m.   
    • Oct. 5-9 from 9:30 a.m. to 12:30 p.m.   
    • Continuously from 8 p.m. Oct. 9 until 3 a.m. Oct. 12 

I-64, Chesapeake Express Lanes:

  • Full Express Lanes closures westbound between the High Rise Bridge and Greenbrier Parkway (exit 289) Oct. 4-10 from as early as 8 p.m. to as late as 10 a.m.  

I-64, HREL Hampton 4C Project:

  • Full ramp closures on I-64 Oct. 4-10 from as early as 9 p.m. to 5 a.m. (Non-conflicting ramp closures may be in place concurrently):     
    • On-ramp from Settlers Landing Road/Woodland Road to I-64 west   
    • Off-ramp from I-64 east to Settlers Landing Road/Woodland Road (exit 267)   
    • On-ramp from Settlers Landing Road/Woodland Road to I-64 east   
    • Off-ramp from I-64 west to Settlers Landing Road/Woodland Road (exit 267)   
  • Alternating, single-lane closures on I-64 in both directions from Mallory Street (exit 268) to LaSalle Avenue (exit 265) Oct. 4-10 from 10 p.m. to 5 a.m.   
  • Brief, intermittent stoppages on I-64 in both directions between Mallory Street (exit 268) and LaSalle Avenue (exit 265) Oct. 5-11 between 12:01 a.m. and 4 a.m. 
  • Long-term, continuous single-lane closure on I-64 in both directions, reducing travel lanes from three to two lanes between Settlers Landing Road/Woodland Road (exit 267) and LaSalle Avenue (exit 265A). 

I-64, HREL Norfolk 1A Project:

  • Alternating single-lane closures on I-64 in both directions from Granby Street (exit 276) to Chesapeake Boulevard (exit 278) continuously from as early as 7 p.m. Oct. 2 to 5 a.m. Oct. 5. (No eastbound work on Oct. 4 between 11 a.m. and 3 p.m.) 
  • Alternating single-lane closures on I-564 from I-64 to Terminal Boulevard: 
    • Eastbound Oct. 4-9 from as early as 7 p.m. to 3 p.m. 
    • Westbound Oct. 4-9 from as early as 9 a.m. to 4 a.m. 
  • Brief, intermittent stoppages along I-64 east between Granby Street (exit 276) and Chesapeake Boulevard (exit 279) Oct. 4-9 from as early as 10 p.m. to 5 a.m.  
  • Brief, intermittent stoppages along I-64 west between Chesapeake Boulevard (exit 279) and Granby Street (exit 276) Oct. 4-10 from as early as 10 p.m. to 5 a.m. 
  • Full ramp closures from I-564 east to I-64 in both directions Oct. 4-9 from as early as 7 p.m. to 5 a.m. 
  • Full off-ramp closures from I-64 west to Granby Street (exit 276A) Oct. 4-9 from as early as 8 p.m. to as late as 7 a.m. 
  • Full on-ramp closures from Patrol Road to I-64 east Oct. 4-9 from as early as 9 p.m. to as late as 7 a.m. 
  • Full off-ramp closures from I-64 west to Tidewater Drive (exits 277A and 277B) Oct. 4-10 from as early as 10 p.m. to 5 a.m. 
  • Full off-ramp closures from I-64 east to Tidewater Drive (exits 277A and 277B) Oct. 4-9 from as early as 10 p.m. to as late as 7 a.m. 
  • Full on-ramp closures on Tidewater Drive in both directions to I-64 west Oct. 4-9 from as early as 8 p.m. to as late as 7 a.m. 
  • Full on-ramp closures on Tidewater Drive in both directions to I-64 east Oct. 4-9 from as early as 10 p.m. to as late as 7 a.m. 
  • Full off-ramp closures from I-64 west to Little Creek Road (exit 276C) Oct. 4-10 from as early as 10 p.m. to 5 a.m. 
  • Full off-ramp closures from I-564 east to Little Creek Road (exit 4) Oct. 4 -9 from 7 p.m. to 5 a.m. 
  • Full on-ramp closures from Little Creek Road to I-64 east Oct. 4-9 from as early as 10 p.m. to as late as 7 a.m. 
  • Single-lane closures on I-64 east on the Willoughby Bay Bridge from 15th View Street (exit 272) to 4th View Street (exit 273) Oct. 5-8 from as early as 9 p.m. to 5 a.m. 
  • Alternating single-lane closures on I-64 in both directions from Granby Street (exit 276) to Chesapeake Boulevard (exit 278) Oct. 5-8 from as early as 7 p.m. to 5 a.m. 
  • Alternating single-lane closures on I-64 in both directions from Granby Street (exit 276) to Chesapeake Boulevard (exit 278) continuously from as early as 7 p.m. Oct. 9 to 5 a.m. Oct. 12. (No eastbound work on Oct. 11 between 11 a.m. and 3 p.m.) 
  • Long-term full on-ramp closure from southbound Tidewater Drive to I-64 east with new left turn at Thole Street to access I-64 east. 

I-64, HREL Newport News/Hampton 4A/4B Project:

I-464, Chesapeake:

  • Full on-ramp closures from Route 17 (Dominion Boulevard) north to I-464 north (exit 17B): 
    • Continuously from 5 a.m. Oct. 4 to 5 a.m. Oct. 5 
    • Oct. 5-10 from 9:30 a.m. to 3 p.m. 
    • Oct. 5-9 from 8 p.m. to 5 a.m. 
    • Continuously from 5 a.m. Oct. 10 to 5 a.m. Oct. 11 
  • Full ramp closures from I-464 north to I-64 east (exit 1) Oct. 5-6 from 9 p.m. to 5 a.m. 
  • Full ramp closures from I-464 south to I-64 west (exit 1A) Oct. 7-8 from 9 p.m. to 5 a.m. 
  • Brief, intermittent stoppages on I-464 south between Military Highway (exit 2) and I-64 interchange (exit 1) Oct. 6-7 from 9 p.m. to 5 a.m. 

I-664, Newport News:

  • Full off-ramp closures from I-664 in both directions to Warwick Boulevard (exit 5) Oct. 10 from 8 a.m. to noon.  

I-664, Hampton: 

  • Full off-ramp closure from I-664 south to Powhatan Parkway (exit 2) Oct. 4 from 7-11:15 a.m. 

I-264, Portsmouth:

I-564 Intermodal Connector, Norfolk:

  • Full off-ramp closures of the Intermodal Connector west ramp to Seabee Road Oct. 5-9 from 9:30 a.m. to 4:30 p.m. 

Last updated: October 2, 2026

© Copyright , VDOT. All rights reserved

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.

Share this page:

Advanced Search Options

Search for:

Search scope:

Type:

Search in:

Date range:

The last

Sort by:

Sign up for:

The Virginia Environmentalist

The daily local news briefing you can trust. Every day. Subscribe now.

By signing up, you agree to our Terms & Conditions.